Three days of power delivery commitment! Wuhan leishenshan hospital is fully electrified

category:Society
 Three days of power delivery commitment! Wuhan leishenshan hospital is fully electrified


Inspection of No.1 distribution box is completed, inspection of No.2 distribution box is completed No. 26 distribution box has been inspected and all of them meet the power transmission requirements. Power transmission ! On the same day, the power grid of leishenshan hospital connected to Huangjiahu, Jiangxia District, Wuhan city was connected. With the order of the on-site project leader, the first and second loop network cabinets of the 10kV military transport supply power to leishenshan hospital, 26 distribution boxes and 2 network ring cabinets generate uniform buzz almost at the same time, and officially start live operation.

Chen Gang, general manager of Wuhan Jiangxia District power supply company of State Grid, said that the double power supply and four circuit power supply mode will greatly improve the power supply reliability of the hospital.

It is understood that since receiving the order of building leishenshan hospital in Jiangxia issued by the anti epidemic headquarters on January 25, State Grid Wuhan Jiangxia District power supply company has refined the safeguard measures, raised equipment and materials, optimized the power supply scheme, and rapidly promoted the construction of power engineering.

It is understood that more than 300 commandos of the company gathered quickly according to the requirements of epidemic situation is order, power supply is responsibility, and put into the construction task of leishenshan electric power project in the fastest, most careful and most rigorous way. By January 28, the company had completed the electrical installation and commissioning of 10 ring cages, 26 box transformers and 6.9 km high-voltage cables, and completed the preparation for power transmission. On January 29, power transmission began.

Next, Wuhan Jiangxia District power supply company will strengthen the special patrol of power supply to leishenshan hospital, ensure the reliable power supply of the hospital, and provide help in safe power use at any time.

It is understood that Wuhan leishenshan hospital is located at the Bank of Huangjia lake, Jiangxia District, the city. According to the latest design, the total construction area of leishenshan hospital is expanded to about 60000 square meters. Among them, the medical isolation area is about 51000 square meters, and the number of beds has increased to about 1600; the medical accommodation area is about 9000 square meters, which can accommodate more than 2000 medical staff.

At present, the general layout of phase I and phase II of leishenshan hospital project undertaken by China Construction Third Engineering Bureau has been designed, the layout of medical staff living area has been completed, and the steel structure drawing of medical technology building has been preliminarily formed. According to the latest design, the total construction area of leishenshan hospital is expanded to about 60000 square meters. Among them, the medical isolation area is about 51000 square meters, and the number of beds has increased to about 1600; the medical accommodation area is about 9000 square meters, which can accommodate more than 2000 medical staff.

At about 12 oclock on January 29, the workers of leishenshan hospital began to receive materials at lunch. Many workers on the construction site take a noon break. They lie on the ground directly, and they go to sleep with a piece of clothes casually. The reporter cried heartache at the scene.