Investigation on Construction Waste Dumping: 300 yuan per vehicle for dregs collected from 10,000 square meters of compound cultivated land

category:Society
 Investigation on Construction Waste Dumping: 300 yuan per vehicle for dregs collected from 10,000 square meters of compound cultivated land


On July 30, the Beijing Municipal Housing and Construction Commission issued a circular on punishment for illegal disposal of construction dregs. Due to the problems existing in the construction site, such as the failure of dregs transport vehicles to go on the road in accordance with the stipulated time, the inadequate implementation of management regulations, and the serious discrepancy between the amount of earthwork for handling the clearance certificate and the actual amount of earthwork, the relevant contractors were subjected to construction. The whole city notified and punished.

According to the investigation conducted by the reporter of the Beijing News for several days, it is found that similar illegal disposal of dregs occurs frequently. There are violations of transportation and dumping of dregs. Because of the low cost of disposal of dregs, a lot of construction waste is transported to the black dregs field without dregs to be disposed of.

In Magezhuang village, Jinzhan Township, Chaoyang District, a compound farmland block covering tens of thousands of square meters receives construction waste at a price of 300 yuan per vehicle. The site has been piled up into hills, and there are still many dregs and dirt trucks dumped into it.

According to the relevant departments, as of June this year, Beijing Public Security Bureau, in conjunction with the Urban Management Committee and other departments, has cleaned up 10 garbage black transfer stations and black dregs and soil yards. Ten cases of illegal dumping of garbage have been uncovered in Yanqing, Fengtai, Fangshan, Shunyi, Chaoyang, Shijingshan, Tongzhou and 106 people have been detained in criminal detention.

Reclaiming dregs from 10,000 square meters reclamation land for 300 yuan a car

In recent months, villagers in Magezhuang Village, Jinzhai Township, Chaoyang District, have gradually become accustomed to shuttling around and raising dusty dregs.

Several villagers said that the trash truck traveled because a large area of compound farmland around the village of Magezhuang turned into a black slag field, receiving construction waste from multiple sites.

The black dregs field in the village mouth is located on the west side of Magezhuang village. This area is enclosed by blue iron. There are signs outside the enclosure that say Compound cultivated land block. The words Compound cultivated land block can also be marked on the enclosure. But standing outside the enclosure, you can see the piles of dregs several meters high in the enclosure, such as the continuous hills.

Entering the site, tens of thousands of square meters of visual observation area, piled up a large amount of dregs, construction waste, climbed up the pile of dregs, you can see a number of dregs trucks in the distance dump dregs, forklift trucks are pushing piles of dregs to low-lying places one by one.

A truck driver told reporters that he had been sending dregs here since a few months ago. The price was 300 yuan for a truck. Its cheap in the dregs yard, so many trucks send dregs here.

According to the regulations, all qualified construction waste disposal sites in Beijing can be inquired on the information sharing platform of comprehensive management and recycling of construction waste in Beijing, but the land for reclamation in Magezhuang Village can not be inquired.

Huang Xiaoshan, a well-known environmental protection personage, said that compound cultivated land is ultimately arable land, and arable land involves food safety issues, which is the highest requirement in the relevant standards of the Ministry of Agriculture of China. When this land is recognized as a compound cropland, in fact, it can no longer be dumped with garbage and dregs. If the scale of the slag field is large and the time is long, the ground should be cleaned up first, and the soil should also be identified to see whether the heavy metal indicators or other indicators meet the standards when they are used in the future.

Huang Xiaoshan told reporters that as long as there is no Beijing Municipal Construction Waste Integrated Management and Recycling Information Sharing Platform in the slag dump, can be identified as a black slag dump.

In addition to the reclaimed land of Magezhuang Village, there are no qualified residue collection sites in East Yantou Village, Mulin Town, Shunyi District, and Fuhao Village, Tongzhou District.

The villagers of Dongyantou introduced that the villages black dregs field was a piece of farmland before. About 45 years ago, some villagers contracted the land to dig sand and gravel, and gradually formed a big pit. Two or three years ago, there were trucks carrying garbage to this side at night, and domestic garbage and construction garbage were all there. Slowly, the pit was filled up.

In the view of villagers in Dongyantou village, if a large amount of garbage is piled here or buried underground, it will inevitably pollute the groundwater source and possibly affect the cultivation of surrounding farmland.

Shangfeng (not his real name) has been a transportation company in Beijing for more than ten years. He told reporters that the current black slag field in Beijing is mainly concentrated in the Fifth and Sixth Rings. There are also some places near Beijing in Hebei Province. There are also some black slag scene to collect slag from the construction site in Beijing.

According to some clues and public reports provided by Shangfeng, according to the statistics of the reporters, the black slag fields in Beijing and its surrounding areas are mainly concentrated in Chaoyang District, Tongzhou District, Fengtai District, Fangshan District, Daxing District and Changping District.

On August 15, 2019, a large number of re-cultivated land was enclosed on the north side of Jiaosha Road in Chaoyang District. The dregs in and out of dump trucks were enclosed by dredgers. Forklifts and excavators were filling the soil.

Running lights under looping wires on illegal dregs and dirt trucks

The existence of black slag field also highlights the phenomenon of illegal transportation of slag trucks.

Heads of transport fleets, dregs yards and sites have their own Wechat groups, which usually inform business needs.

Reporters have noticed that in the above-mentioned Wechat group, advertisements for business often refer to the common names of the first four to the last eight and the ten wheels plus the gang, and the prices of each model are also different.

Wang Tao, Secretary-General of the Beijing Transport Chamber of Commerce, explained to reporters that according to the Beijing local standard DB11/T1077-2014, the hopper standard of dregs trucks is 5.6m x 2.3m x 1.5m. The hopper also needs to be equipped with tarpaulins. Because there are 10 tires in the hopper, it is also commonly known as the (standard) ten-wheeled or green leather truck, and the hopper volume of such dregs trucks is 5.6m x 2.3m x 1 Nearly 20m, almost all other specifications of dregs trucks belong to irregular vehicles.

Among the non-conforming vehicles, there is a modified truck, commonly known as the 10-wheeled plus high gang, which is similar in shape to the standard 10-wheeled truck, but has a higher bucket and does not install tarpaulins. The rest is what the industry commonly calls the front four and back eight. The front four and back eight refers to 12 tires of this kind of truck. Among them, the large front four and back eight truck bucket size can reach 8.2 m x 2.4 m x 2.3 m, and the volume of the truck bucket is about 45 M.

For the convenience of construction, many construction sites prefer to choose front four back eight with larger carrying capacity for transportation.

According to Wechat Group news, in the early morning of August 2, a reporter at a demolition site near Donghai Hongcun in Shunyi saw that from time to time front four and back eight passed through the intersection, and a black car stopped at the gate of the construction site to issue dregs and dirt tickets for trucks coming to transport dregs and dirt. After that, cash was exchanged for tickets.

Reporters noticed that in only half an hour, there were eight front four back eight trucks driving into the construction site. At about one oclock, a truck loaded with construction waste came out of the construction site. The construction waste in the truck bucket exceeded the carriage, and the dregs scattered from time to time. The license plate on the truck body was covered by soil, which was difficult to recognize. It disappeared in the night all the way through the red light.

A truck driver told reporters that it takes a long time to process the residue truck clearance permit. In addition, the residue clearance certificate requires that vehicles have a fixed route, and different routes need to be dealt with again. Some cars work in small construction sites, they are pulled out in a few days, and they have to re-license other sites, so many cars simply refuse to license, Some cars, even if they meet the required standard of ten wheels, are likely to be undocumented.

During many days of car-following visits by journalists of the Beijing News, the situation of large truck dregs scattering, shielding the number plate, running red lights and so on appeared frequently.

Unlicensed transportation, blocking the number plate and running the red light are all common problems of dregs trucks. Shang Feng told reporters that since July when the two construction sites were notified of their illegal disposal of waste, many sites have been more careful than before, and more standard vehicles with permits have been chosen when using the vehicles. Many top four and back eight fleets have less business than before, and the dregs have also begun to go to Guan and Langfang in Hebei Province. Lets go and unload.

On August 2, 2019, at Shunsha Road, Shunyi District, Beijing, a large car entered the construction site early in the morning to haul dregs and soil.

A car can be 300 yuan cheaper to collect land at a low price.

Why is business flourishing in black slag field? Reporter survey found that the reason why many transport fleets choose the black slag dump is mainly due to the lower price of dumping garbage and slag.

Reporters have joined several related Wechat groups in Beijing, such as Mechanical Transport to Admit Earthwork Project, Tongzhou Earthwork Group, Beijing Earthwork Group, and so on. The members of the group are basically more than 400 people, and a large number of advertisements are published in each Wechat group every day. Such as Shangezhuang * * out of the mixed soil, loading at 7 p.m. and stopping at 5 a.m., front four or back eight thousand yuan, green car 600 yuan, cash! Langfang Wanzhuang harvest, construction waste, cars and cars can be, the site is large. Wait.

Through the advertisements in the Wechat group, the reporter has made contact with several black dregs. On August 7, a man who advertised in a group told reporters that his dregs yard is located in Guangyang District, Langfang City, Hebei Province. It can collect construction waste, but not domestic waste, 400 yuan per car.

Another advertisement claims that northern Yaoshangcun in Fangshan District collects all kinds of dregs. Contacts told reporters, 300 cars, only 10 rounds.

The dregs collected in the black dregs field are priced by cars, but in the regular construction waste disposal yards, they are priced by tons.

Reporters contacted several regular construction waste disposal sites in Beijing. The charge standard for dregs ranges from 20 yuan to 45 yuan per ton. According to the specifications of the regular dregs transport vehicle, the weight of each vehicle is 30 tons, which means that the dregs of each vehicle should pay 600 yuan to 1350 yuan to the regular clearing house.

Shangfeng, who has dealt with the transportation of dregs all the year round, said that in the black dregs yard, the charge for a car of dregs is generally between 300 yuan and 600 yuan, while the regular absorption yard is far above that price. A car is at least 300 yuan apart. A motorcade pulls dozens or even hundreds of cars every day. Shang Feng said that many fleets only delivered to the black dregs field, the price difference is the most important reason.

On August 14, the reporter arrived at a black cinder field on the north side of Fuhao Village in Tongzhou District, which is located on the east side of Bifu Road.

Dreg trucks are very common on Bifu Road even in daytime. On the afternoon of the 14th, in just one hour, more than 10 dregs trucks loaded with dregs came here to unload the soil. At about 3 p.m., two dregs trucks loaded with dregs entered the above-mentioned area. At this time, there is already a excavator and a number of dregs trucks in the site to deal with the dregs.

After discharging the dregs, the two dregs returned to the site together. Reporters followed, these dregs vehicles ran red lights all the way, one of them could see the license plate from the front, but the license plate behind the vehicle has been unable to recognize, the car body according to the regulations sprayed license plate number also has obvious smear marks. Two cars ran through the red light all the way through the residential area and returned to a construction site on the northeast side of the electronic city community of Half-cut Tower Road in Chaoyang District.

In order to prevent such problems as traffic police reconfiguration, overloading and undocumented transportation, many slag convoys also have special personnel responsible for car protection.

On the evening of August 7, the reporter followed Shangfeng from Beijing to Guan, Hebei Province. On the highway, he saw more than 10 vehicles carrying construction waste. At Guan toll station, a row of front four back eight trucks stopped in front of the toll station, and not far from the exit of the toll station, several cars stopped at the roadside, and the driver was asking people about the road condition.

Shangfeng told reporters that these car drivers are so-called car-keepers, they explore the road in front of the toll station to see if there is a traffic police car, and so on conditions permit, before notifying the truck behind the stop. Until the early morning of August 8, when reporters returned to Beijing via Guan toll station, they could still see more than 10 dregs and dirt trucks parked here.

On August 15, 2019, a large number of re-cultivated land was enclosed on the north side of Jiaosha Road in Chaoyang District, and a large amount of construction waste was piled up in the enclosure.

Rejection of Construction Site Residue from Partial Regular Reclamation Sites

Wang Tao, secretary-general of the Beijing Transport and Commerce Chamber, told reporters that besides the low fee standard of the black slag soil yard, there are still some irregular operations of the regular slag soil yard, which also catalyzed the irregular dumping of some transport fleets in the black slag soil yard.

Wang Tao said that in recent years, the construction volume in Beijing is relatively large, and the production of construction waste is also large, but the acceptable absorption area has become saturated. In order to ensure their own qualifications, some slag disposal sites have appeared the phenomenon of selling only agreements and not collecting slag.

Its hard for them to apply for a clearing house. If they fill it up quickly, they cant continue to make money. There are also some absorption sites, which only recycle a part of good loess, good cement blocks and other slag that can be reused. Wang Tao believes that the current distribution of construction waste disposal sites in Beijing is unreasonable, mostly in Shunyi, Miyun and other relatively remote areas. If it is a project in the urban area, the cost of transporting dregs to these areas is too high, which also leads to illegal dumping of dregs by convoys.

In some formal clearance agreements issued by journalists, many contents are not clear. Some contracts simply state Party A and Party B, and the tonnage of dregs.

Shang Feng showed reporters a snapshot of a micro-message chat, which showed that it cost hundreds of thousands of yuan to handle a settlement agreement. Look, I signed an agreement, in fact, I will not unload the soil here. Even if they used to unload, they will not accept it. At most, they will only collect a part of the recyclable residue, such as construction waste, which will definitely not be collected. These are unwritten regulations in the industry. We pay him for the certificate. Recently, there has been a lot of tightness. No acquaintance can do it at all.

Shangfengs certification refers to the start-up permit of the construction site. According to relevant regulations, the construction site must have a residue absorption permit before it can handle the start-up permit.

Shangfeng explained to reporters that the construction site needs to start, in accordance with the principle of who produces and who absorbs, the construction party should deal with the dregs and soil absorbance certificate, but because the processing of the absorbance certificate often generates some costs, many construction parties have pushed this task to the transport company on the construction site.

A person in charge of a transport convoy cited an example, saying that the transportation company contracted the transportation task on the construction site, which was settled according to the actual amount of earthwork transported. All kinds of expenses incurred during the whole transportation process are borne by the transport party itself, one cubic metre of dregs, with prices ranging from several tens of yuan to one cubic metre, and are calculated at 50 yuan and one cubic metre. Each square earth weighs about 1.5 tons, and the regular clearing house charges 30 yuan per ton. With standard ten wheels to transport goods, a vehicle of 20 cubic meters is about 30 tons. The transportation company takes 1,000 yuan from the construction party, and then gives 900 to the clearing house. Counting the fuel cost, drivers salary and vehicle wear and tear, it is sure to lose money.

Shang Feng said that many people will not strictly deal with the actual production of the site when they apply for residue clearance certificate, but only spend the least money to handle the clearance certificate. This action will also lead to the above phenomena in the public information of the project that the amount of earthwork for clearance certificate is not in conformity with the actual amount of earthwork. And more construction waste goes to low-cost black slag dump.

Wang Tao told reporters that in the field of engineering construction and dregs transportation, according to experience, there are some algorithms. For example, in the demolition project, 1.2 tons to 1.6 tons of construction waste will be generated for every 1 square meter building demolished; in the case of a new project, a new 10,000 square meter building will generate 500 to 600 tons of construction waste.

By inquiring the source information column of Beijing construction waste comprehensive management and recycling information sharing platform, we can find that some projects do have the phenomenon that the amount of earthwork absorbed is not consistent with the actual amount of earthwork.

For example, the building area of an apartment demolition project in Houshayu Town, Shunyi District, is 208877 square meters. However, in its public information, construction waste is only 3000 tons. However, in the public information of the relocation project of a hospital in Beijing with a building area of 3190 square meters, only 26000 tons of Engineering trough soil were found.

On August 15, 2019, several plots of land were enclosed in the north of the East Yantou Village, Mulin Town, Shunyi District. Domestic garbage and construction garbage were dumped inside.

Strict supervision and elimination of collecting money but not land

Before being notified of the illegal disposal of dregs in Beijing construction projects, the relevant departments in Beijing have repeatedly cracked down on the illegal dumping of garbage.

According to Beijing police, since 2019, the Beijing Public Security Bureau has joined forces with the Urban Management Committee to crack down on illegal dumping of garbage. Up to now, joint law enforcement has been carried out more than 20 times, more than 70 locations have been arranged, 10 black waste transfer stations and black residue soil sites have been cleared, and 10 cases of illegal dumping of garbage have been uncovered in Yanqing, Fengtai, Fangshan, Shunyi, Chaoyang, Shijingshan and Tongzhou, and 106 people have been detained in criminal cases.

Huang Xiaoshan, a well-known environmental protection personage, said that Beijing is now speeding up the construction of landfills and treatment sites for domestic waste, and the total amount of construction waste is often larger than domestic waste. Beijing should speed up the construction of reuse projects for construction waste and reduce the amount of construction waste landfill through resource reuse. As far as I know, Daxing There is a large-scale project of reuse of construction waste resources in the district. The government should speed up the pace, rationalize the layout and increase the disposal capacity of reuse of construction waste resources.

Wang Tao said that their long-term research and development found that the current construction waste landfills in Beijing can not meet the needs of the market, but these regular landfills have not been strictly monitored, resulting in the phenomenon of selling dregs to absorb agreements to collect money without collecting dregs.

In order to standardize the order of comprehensive management and reuse of construction waste in Beijing, and ensure the implementation of reduction of construction waste sources, Wang Tao suggested that government departments should make appropriate adjustments and reforms, introduce more targeted laws and policies, and change the passive situation of supervision; the industry should also strengthen self-discipline, from the following aspects: From the perspective of promoting the sustained and healthy development of the industry, enterprises are called upon to regulate their operations. In addition, relevant enterprises should also fulfil their social responsibilities, and more importantly, they need the supervision of third-party social forces such as the media.