Nearly 500 households living in deep pits in a small district of Henan Province have not completed the housing exchange for three years.

category:Society click:323
 Nearly 500 households living in deep pits in a small district of Henan Province have not completed the housing exchange for three years.


Core Tip | I spent half of my life buying a house. I found out that I had entered the pit after I moved in with joy. Looking at the coming New Year, nearly 500 owners of 1885 District, California, Luoyang High-tech Zone, are not happy: because of the problems left over from the construction of the community project, they have lived in a pit more than 10 meters deep for nearly three years, and many people have cracks in different degrees on the walls of their homes.

Tell about

The new house which has been handed over for three years has not been completed yet?

Recently, Ms. Qiao, who lives in Luoyang High-tech Zone, dialed Dahe Bao Luoyang Central Hotline to reflect that her house has been handed over for three years, but it has always been a half hanging project. Halfway through the construction of shops on the floor, the new house became a rotten tail building, which made them unbearable.

Ms. Qiao told reporters that it had been three years since her house was delivered in November 2015, but the shop downstairs had not been built yet. As the project was in progress, there was a big pit on the side of the house. Water accumulated in rainy season is like a swimming pool. Ms. Qiao said that enthusiastic neighbours formed a group of owners. Every day, people brushed screens on the matter. Nearly 500 owners, including her, were worried about the structural safety of the building.

On December 18, in the 1885 District of California on Jiudu West Road, the reporter met three owners, Ms. Qiao and Mr. Guo.

Mr. Guo told reporters that he bought the apartment to support his parents. At the beginning, the price per square meter was higher than nearly 1,000 yuan for other buildings in the same area. It was purchased for the promotion of high quality in the sales office.

However, after three years of housing intercourse and almost two years of residence, the house has not been built yet. When my parents live in it for one day, I worry about one day. Mr. Guo said.

The residential building adjacent to the district is a deep pit more than ten meters deep.

Scene one

Residents live in pits up to 10 meters deep.

The three-year-old house was not completed, the crux of which lies in the rotten tail shops downstairs.

According to reports, the northernmost floor 8 and 9 of the district is the shop that has not yet been completed.

Reporters at the scene saw that in the northwest corner of the district, on the side of the adjacent peoples recreation area, is a deep pit of about three floors. On the side of the deep pit is the 9th floor of the district, one to three floors are shops, and upstairs are the houses of the owners.

Because the plot is built on the slope, the unfinished shop on the bottom floor of Building 9 and the surrounding mounds form a large pit with the deepest depth of about 10 meters.

According to Ms. Qiaos video, during the rainy season, the pit was covered with yellow mud. Ms. Qiao said that because of the poor terrain, when it rains, the rainwater pours back. The water flows like a waterfall. The deepest part of the water is nearly two meters. The building is so soaked in water, the owners are worried about safety.

Deep pits are full of water in rainy season, up to two meters deep (respondents photo)

Subsequently, the reporter accompanied the owner to the North floor of the building, the first floor of the unfinished shop, to see that the pavement at the bottom of the pit has not been hardened, and the facade outside the building can clearly see the marks soaked by water.

Scene two

Residents who have been living in new houses for more than a year have experienced wall cracks

The most serious impact of the deep pit is nearly 500 households in the 8th and 9th buildings of the community. According to Ms. Qiao, according to the owners statistics, the occupancy rate of these two buildings is 90%, and most of them have cracks in the walls of their homes.

In the quiet home of the owner of Unit 2 of Building 9, the reporter saw that there was a crack about 3 meters long from the bottom to the top of the wall opposite to the main and secondary beds, which penetrated the front wall in depth, and the crack of the secondary beds extended to the roof.

At the owners house of Unit 1 of the building, the reporter saw two bedroom walls with cracks about one meter long. The initial crack was about 20 centimeters, not so long. Owner Wenwen told reporters that her house was renovated in 16 years. Before renovation, cracks had been found on the walls, but it felt that it was a minor defect and did not care.

Less than one year, cracks appear on the wall of the owners house

New house occupancy for a year, the cracks grow longer and longer, learn that other owners also have such problems, it began to tense up. Im pregnant and I dont sleep well at night. Wen Wen said.

Reporters in the list collected by enthusiastic owners found that cracks from 70, 80 centimeters to the entire wall height, and so on, many owners have encountered varying degrees of wall cracks.

Scene three

Simple shelter for steel bars exposed in building

Next to the side of the deep pit is the resident of Unit 3, Building 9 of the community.

Reporters entered one of the residentshomes, looking down from the west side of the house, in addition to the deep pit, but also hanging out the steel bar directly inserted into the building, without any protection treatment.

What naughty child you meet climbs high and falls low, and you cant imagine it later. The owner, Ms. Li, said that there was no fence on the north side of the community, only a guardrail more than two meters high, which was close to the green leisure area of the community. On the one hand, it is a pleasant residential landscape, on the other hand, it is a rotten tail project, which makes the owners mind not taste.

What worries the owners most is whether the untreated reinforcing bars, which have been corroded by the wind and sunshine for many years, will affect the structural safety of the building?

Scene four

Unmanned construction waste dumped at random in uncompleted tail shops

The thought of living in a deep pit and pillowing the exposed steel bar makes it difficult for owners who have spent half their lives buying houses to accept.

In addition to the structural safety of the building itself, there are also hidden dangers such as fire protection and public security brought by the rotten tail shops, which make the owners uneasy.

The third storey on the ground floor is separated from the first floor and the second floor and the first wall of the building they live in. Mr. Guo said that although the property will lock several doors, because the back of the building is sparsely populated and the lock is relatively simple, it is easy to be followed by illegal elements.

Reporters saw on the spot, near the side of the pit, piled up? A lot of construction waste. In addition, the ground is littered with various kinds of domestic waste, as well as fragmented insulation layer.

Somebodys barbecuing here in summer. Mr. Guo said that when enthusiastic owners came to inspect the building, they often found burning marks. If flammable goods were ignited carelessly, the residents upstairs would suffer from rice seedlings.

Developer: I dont accept interviews

When the shop on the ground floor is not completed, the house will be put into use. Owners are worried about the structural safety of the building. Do developers have further maintenance measures?

It is reported that Luoyang California 1885 District is Henan Xinhengshun Real Estate Co., Ltd. Dahe Newspaper reporter landed on the companys official website, has been unable to find the web page. According to the data of Tian Eye Check, the registered capital of the company is 70 million yuan, registered on November 10, 2008. The companys profile column says that the company is committed to building high-quality housing for the middle class of society. Subsequently, the reporter contacted Chen Weifeng, the project manager of Xinhengshun Real Estate Developer. When the reporter indicated his intention to interview, he immediately hung up the phone. Subsequently, the reporter sent a short message to his mobile phone on the issue of whether the second phase of the residential area meets the standard of house delivery and whether the completed acceptance record form has been obtained, and the other party answered by short message: I do not accept interviews. Why is the shop project on the ground floor of this district suspended? Does the house meet the housing delivery standard? Does it get the Record Form for Acceptance and Acceptance of Completion? Dahe Daily reporters will continue to pay attention to this matter. Source: Dahe Net - Dahe Newspaper Author: Liable Editor of Li Shaomen: Su Hong-hung_NBJ9980

It is reported that Luoyang California 1885 District is Henan Xinhengshun Real Estate Co., Ltd. Dahe Newspaper reporter landed on the companys official website, has been unable to find the web page. According to the data of Tian Eye Check, the registered capital of the company is 70 million yuan, registered on November 10, 2008. The companys profile column says that the company is committed to building high-quality housing for the middle class of society.

Subsequently, the reporter contacted Chen Weifeng, the project manager of Xinhengshun Real Estate Developer. When the reporter indicated his intention to interview, he immediately hung up the phone. Subsequently, the reporter sent a short message to his mobile phone on the issue of whether the second phase of the residential area meets the standard of house delivery and whether the completed acceptance record form has been obtained, and the other party answered by short message: I do not accept interviews.

Why is the shop project on the ground floor of this district suspended? Does the house meet the housing delivery standard? Does it get the Record Form for Acceptance and Acceptance of Completion? Dahe Daily reporters will continue to pay attention to this matter.